INPEX ICHTHYS GEP
CPPI Logistics Group had the honor to handle all aspects of the loadout operations as it was engaged by BSI (Bredero Shaw Indonesia) for Trucking and On Shore Riggers and by Spliethoff for onboard Stevedoring and Ship Agency services. The first vessel was called on 4th May 2015 and the last shipment was on 12 October 2015. The load-out was completed successfully without any material incident or Loss Time Injury.
This was hailed by the client as the best team effort and best facilities so far, such project in the world.
- Shipments = 51
- Pipe Joints = 35,432
- Revenue Ton = 613,982